Influence of seasonal factors in the earned value of construction

Check for updates


Authors

Juan Pedro Ruiz-Fernández Affiliation:
Departamento de Ingeniería Civil y de la Edificación. Universidad de Castilla-La Mancha, Ciudad Real, Spain
, Javier Benlloch Affiliation:
Departamento de Construcciones Arquitectónicas. Universidad Politécnica de Valencia, Gandia, Spain
, Miguel A. López Affiliation:
SIDIS Research Group, Department of Mathematics, Institute of Applied Mathematics in Science and Engineering (IMACI), Polytechnic School of Cuenca, University of Castilla-La Mancha, 16071 Cuenca, Spain
and Nelia Valverde-Gascueña Affiliation:
Departamento de Ingeniería Civil y de la Edificación. Universidad de Castilla-La Mancha, Ciudad Real, Spain


Abstract

The objectives in each construction process can be multiple. However, the constructions have to be carried out under some restrictions concerning price and terms. They constitute some strategic and interdependent goals. In other words, “time is money”. Several papers support that seasonal effects influence the execution rate of construction. Thus, most of them try to improve the forecasts by evaluating and joining them to the planning, although always measuring their influence indirectly. In this paper, we suggest a methodology to directly measure the influence of the seasonal factors as a whole over the earned value of construction. Additionally, we apply it to a certain case study regarding the subsidised housing of public promotion in the Castilla-La Mancha region (Spain). It is worth mentioning that our results are clarified: we have calculated the average monthly production for each month a year with respect to the annual monthly mean. Moreover, the differences regarding the average monthly production we have contributed are quite significant, and hence they have to be taken into account for each earned value forecast so that a project becomes reliable.


Keywords

Seasonal factors, Earned value, Cash flows, Construction, 00A69, 62-07, 62P30


Citation

Ruiz-Fernández, J. P., Benlloch, J., López, M. A., & Valverde-Gascueña, N. (2019). Influence of seasonal factors in the earned value of construction. Applied Mathematics and Nonlinear Sciences, 4(1), 21–34. https://doi.org/10.2478/AMNS.2019.1.00003
37 Total citations
16.66 FWCI
1 Recent citations
(2 years)
13 References
Open Access Yes
View full metrics

Published by: Engineering Journals

Engineering Journals Logo